$2 billion of border wall money sits idle in bank as Biden leaves busiest migrant area wide open

.

RIO GRANDE VALLEY, Texas Most of the $2 billion that Congress set aside for 110 miles of wall and technology in the busiest region of the U.S.-Mexico border sits in the bank unspent as thousands of migrants illegally cross each day.

Eighty-nine miles of the project is unfinished, along the winding Rio Grande River that divides the two countries. While President Joe Biden’s administration shut down wall construction funded through diversions from the Trump administration, the project was approved and funded by the House and Senate. Besides this section, most of the wall projects funded by Congress during the Trump administration have been completed.

A senior Border Patrol agent said the project costs about $20 million a mile, and it is not clear why the final 89-mile stretch has been stalled or who will make the final call on whether to spend the money.

“We work for the government. We work for the Department of Homeland Security, so the secretary,” the official said, who was only able to speak anonymously with the Washington Examiner during a congressional tour this week. “He gets his orders from Congress and also from the executive branch, right? But ultimately he’s appointed, right? So he’s our boss. We do what he tells us.”

Top Republicans have moved to force the Biden administration to build the portion of the wall that was appropriated by Congress. Sen. Shelley Moore Capito, the top Republican on the Senate Appropriations Subcommittee on Homeland Security, and Vice-Chairman Sen. Richard Shelby of Alabama have asked for the Government Accountability Office to intervene and decide whether Biden violated the Impoundment Control Act by suspending all projects without providing legal justification. Such a finding could give them reason to sue.

EXCLUSIVE: INSIDE BORDER PATROL’S STRUGGLE TO PROMOTE HISPANIC AGENTS

Ten projects totaling 110 miles were slated for this 320-mile stretch of border river. Congress could repurpose the remainder of the $2 billion to fund only technology at the border even though the money was originally meant to cover the cost of the wall, the levee system used to prevent floodwaters from entering town, roads, and lighting along the wall.

Wall construction in the Rio Grande Valley first began in the early 2000s after Congress funded 55 miles of the barrier. That 10-foot wall is in less-than-ideal condition and far less capable of preventing illegal crossings compared to the 30-foot wall that has become the standard.

IMG_4982.jpg
The 18-foot border fence sits atop a levee wall in the Rio Grande Valley of Texas.

The project has long portions of fencing that stretch 32 feet high. The fence sits atop the concrete levee wall, which is 14 feet and serves as a wall to floodwaters from the river. Gates that would allow Border Patrol to drive past the wall and closer to the river have not been powered and thus cannot be opened. In other spots of the wall, there are no gates so National Guard officials sit and man the opening in case migrants are spotted coming through.

The wall here is black in some areas and brownish-red in others. While former President Donald Trump had called for the fence to be painted black because he said it looked better, the official said it actually serves an important purpose.

“The darker color stuff heats up, gets hotter. It’s also slicker. In other places where you have the natural rust on it, that rust actually makes like a grip-like feature,” said the official. “When you don’t have rust, it’s slick like this. It’s harder to grab a hold of [and climb].”

The Border Patrol brought in outside experts from Johns Hopkins University in Baltimore, Maryland, to see what combination of infrastructure and technology would help agents gain control of the border. While Democrats in Congress and the Biden administration may be inclined to spend the remaining money on technology and not wall construction, the Border Patrol official said “technology doesn’t slow them down.”

“We’ll take the technology, but we won’t gain operational control over the area. It’ll help, but we won’t accomplish our mission,” the official said.

CLICK HERE TO READ MORE FROM THE WASHINGTON EXAMINER

Even if the Biden administration gave the green light for construction to continue, it would take six to eight months to screen and vet the thousands of workers needed for the projects. It would also take time to get the equipment and supplies back on site, according to the border agent. But despite the significant amount of work, it is what the Border Patrol is hoping comes to fruition.